General Contracts
| CONTRACT TITLE |
Cheltenham General Hospital - Various |
CLIENT |
Glos Hospitals NHS Foundation Trust |
PROJECT MANAGER |
Estates Department |
MAIN CONTRACTOR |
Various |
CONSULTANT |
ESDP Limited |
CONTRACT VALUE |
£50,000 - £2,000,000 |
DESCRIPTION OF WORKS |
Mechanical and/or Electrical services refurbishment and installations in the following areas:-
St. Luke’s Basement, CSSD Dept, Oncology Extension, Retinal Screening, CT Scanner, Relocatable Cardiac Unit, Site Wide Fire Alarm Cabling upgrade/installation (in conjunction with Protec Fire Detection), MRI Chiller Relocation, Radiology Rooms 1&4, X-Ray Room 8, Hartpury Suite, Linac/Linear Accelerator |
| CONTRACT TITLE |
Tidworth SFA Phase II |
CLIENT |
MOD |
PROJECT MANAGER |
n/a |
ARCHITECT |
n/a |
MAIN CONTRACTOR |
Laing O’Rourke |
CONSULTANT |
Hoare Lea |
CONTRACT VALUE |
£2,000,000 M&E Total |
DESCRIPTION OF WORKS |
Installation of mechanical and electrical services to 263no. new married quarters in Tidworth |
Back to top
| CONTRACT TITLE |
Double Reynolds & Vinings Warehouse, Gloucester Docks |
CLIENT |
Crest Nicholson |
PROJECT MANAGER |
n/a |
ARCHITECT |
Hemingway Architects |
MAIN CONTRACTOR |
Barnwood Construction |
CONSULTANT |
Jones King Partnership |
CONTRACT VALUE |
£1,000,000 M&E Total |
DESCRIPTION OF WORKS |
Installation of mechanical and electrical services to 71no. newly refurbished apartments in warehouse developments |
Back to top
| CONTRACT TITLE |
Plot 3200, Shannon Way, Tewkesbury – Production Building & Office Block |
CLIENT |
Group 4 |
PROJECT MANAGER |
Gleeds Management Services |
ARCHITECT |
Roberts Gardner |
MAIN CONTRACTOR |
Britannia Construction |
CONSULTANT |
Ove Arup |
CONTRACT VALUE |
£2,500,000 M&E Total |
DESCRIPTION OF WORKS |
Installation of mechanical and electrical services to new build offices and Production Warehouse including air conditioning and ventilation |
Back to top
| CONTRACT TITLE |
Maindy Road, Cardiff |
CLIENT |
- |
PROJECT MANAGER |
- |
MAIN CONTRACTOR |
Wigley Fox |
| ARCHITECT |
Phaze Electrical |
CONSULTANT |
Wigley Fox |
CONTRACT VALUE |
£1,170,000 |
DESCRIPTION OF WORKS |
Installation of mechanical services to student accommodation in Maindy Road, Cardiff |
Back to top
| CONTRACT TITLE |
North Road, Cardiff |
CLIENT |
- |
PROJECT MANAGER |
- |
ARCHITECT |
Rio Architects Limited |
MAIN CONTRACTOR |
Stradform Limited |
CONSULTANT |
White Young Green |
CONTRACT VALUE |
£1,500,000 |
DESCRIPTION OF WORKS |
Installation of mechanical services to new student accommodation including the provision of solar heating and electricity |
Back to top
| CONTRACT TITLE |
New Monkey House, Bristol Zoo, Bristol |
CLIENT |
Bristol Zoo |
PROJECT MANAGER |
- |
| ARCHITECT |
Rio Architects Limited |
MAIN CONTRACTOR |
E G Carter & Co. Limited |
CONSULTANT |
White Young Green |
CONTRACT VALUE |
£1,500,000 |
DESCRIPTION OF WORKS |
Installation of mechanical & electrical services to the new Monkey House at Bristol Zoo including lighting, heating, ventilation etc. |
Back to top
| CONTRACT TITLE |
St. Paul’s Church, Bristol |
CLIENT |
St. Paul’s Church |
PROJECT MANAGER |
Philip Hughes Associates |
ARCHITECT |
Philip Hughes Associates |
MAIN CONTRACTOR |
Carrek Limited |
CONSULTANT |
EEP |
CONTRACT VALUE |
£60,000 |
DESCRIPTION OF WORKS |
Mechanical services refurbishment – new boiler plant & heating system |
Back to top
| CONTRACT TITLE |
Beaufort Community School |
CLIENT |
Gloucestershire County Council |
PROJECT MANAGER |
Symonds Group |
| ARCHITECT |
Glos County Council |
MAIN CONTRACTOR |
E G Carter & Co. Ltd. |
CONSULTANT |
GKSA |
CONTRACT VALUE |
£300,000 (various projects) |
DESCRIPTION OF WORKS |
Mechanical services installations to various areas around the school including new boiler & heating systems and toilet block refurbishment |